Day summary
On the first day of the week, we were met by the head of IT department in the customer site.. Suddenly he made a request that is awesome and bad at the same time.. He wanted to deliver 1500 users to the help-desk by the end of the week… So this was awesome because it means that we can deliver users faster, but it was bad at the same time because it meant that we need to setup more VM instances to be used for the migration work and we need to order more licenses for each user, and they have multiple domains, so it meant we needed to order multiple licenses for each domain to cover the amount of users…
We received the list of the 1500 users and I sorted them out based on the domain… This was a great opportunity also to show the customer … Read the rest “A story of a project: 3600 users to G Suite in 60 days! – Day 6: Going even faster with the migration”